848 trees give way to Burgos wind farm

By Leilanie G. Adriano
Staff Reporter

BURGOS, Ilocos Norte—More trees have to fall, to give way to the on-going construction of the largest wind farm in the Philippines, which is targeted for commissioning in the last quarter of this year.

After eight months of full construction work, the Burgos wind project (BWP) of the Lopez-led Energy Development Corporation (EDC) in Ilocos Norte has started installation work and transportation of huge wind turbines in the area following grounds excavation and backfilling operations along the sprawling 600-hectare coastal and mountainous areas covering Brgys. Saoait, Poblacion and Nagsurot here. 

“For any kind of development, some things have to be sacrificed,” said provincial environment and natural resources officer Juan delos Reyes in allowing the cutting of 848 trees and earth balling of 1,944 tree saplings more to make way for the 87-MW Burgos wind farm .

To date, the Department of Environment and Natural Resources (DENR) has granted at least two special cutting permits to EDC for the cutting of these towering trees covering several barangays of Burgos town where the large scale Vestas V90-3.0MW wind turbines and ancillary plant will be erected.

EDC’s special cutting permit no. 2013-04 and 2013-05 covers the cutting of 848 trees. About 732 of these have already been felled. 

Early this month, Reman Chua, project manager of the BWP has requested for the extension of the permit as more than 100 trees included in the inventory have yet to be cut under the special cutting permit.

According to Chua’s letter, the request for extension was due to a delay in meeting the scheduled cutting activity because workers had a hard time passing through the slope and stony formation surrounding these trees while mitigating soil erosion.

Once operational, the BWP is expected to generate about 233GWh of electricity a year, enough to power more than a million households and augment the Luzon grid’s dependable capacity.

In the next ten years, the Luzon grid is expected to be in need of additional 4,200MW.

Aside from the wind farm, the project also includes 1,115kV transmission line connecting the wind farm from the Burgos substation to the Laoag substation of the National Grid Corporation of the Philippines, as well as the expansion of the switchyard/substations.

The BWP broke ground on April 17 last year and started the major civil works of constructing at least 29 large footings with a volume of approximately 500 cu. M per footing foundation.


First Balfour signed a P2.4 billion deal with Vestas Wind Systems of Denmark, the world’s largest wind manufacturer for the civil works of the 87 MW wind power farm. It is expected to be completed in October 2014.

Comments

Popular posts from this blog

Empanada festival: A celebration of good taste and good life

By Dominic B. dela Cruz & Leilanie G. Adriano Staff reporters BATAC CITY—If there is one thing Batac is truly proud of, it would be its famous empanada-making business that has nurtured its people over the years. Embracing a century-old culture and culinary tradition, Batac’s empanada claims to be the best and tastiest in the country with its distinctive Ilokano taste courtesy of its local ingredients: fresh grated papaya, mongo, chopped longganisa, and egg. The crispy orange wrapper and is made of rice flour that is deep-fried. The celebration of this city’s famous traditional fast food attracting locals and tourists elsewhere comes with the City Charter Day of Batac every 23 rd  of June. Every year, the City Government of Batac led by Mayor Jeffrey Jubal Nalupta commemorate the city’s charter day celebration to further promote its famous One-Town, One Product, the Batac empanada. Empanada City The Batac empanada festival has already become...

2020 Laoag City Traffic Code

  Republic of the Philippines Province of Ilocos Norte CITY OF LAOAG   SANGGUNIANG PANLUNGSOD   EXCERPT FROM THE MINUTES OF THE 58 TH REGULAR SESSION OF THE 11 TH SANGGUNIANG PANLUNGSOD OF LAOAG HELD AT THE SANGGUNIANG PANLUNGSOD SESSION HALL, LAOAG CITY ON OCTOBER 14, 2020. PRESENT: 1.        Hon. Vicentito M. Lazo                                                 City Vice-Mayor/Presiding Officer Hon. Juan Conrado A. Respicio II                                              S.P....

Marcos town celebrates 3rd Pinakbet Festival

MARCOS, Ilocos Norte—Taking pride of this town ’s favorite Ilo cano dish, locally known as pinakbet, a mix of indigenous vegetables steamed in fish sauce, residents here ushered the opening of the third Pinakbet festival. “Pinakbet” came from the contracted Ilokano word ‘pinakebbet ’ which means “ shrunk ” or “shriveled.” As a way of thanksgiving, the Pinakbet festival is a repository of the town ’ s “ani” [harvest] festival being celebrated every month of March but this was later moved to December to accommodate more balikbayans wanting to join the festivity. Residents in this agricultural town derived most of their income from the harvest of high value crops, including rice, tobacco and corn as staple crops. This year, the week-long festivity highlighted a grand parade around the town plaza and a pinakbet cook fest at the municipal gymnasium to showcase the best pinakbet in town. A boodle fight followed suit. Earlier, a fun run was participated by various groups ...