By Leilanie G. Adriano (Staff Reporter) LAOAG CITY—Three colossal projects in the province of Ilocos Norte are taking their tool in view of the ongoing coronavirus disease 2019 (COVID-19) pandemic, which delays the delivery of equipment and construction materials including skilled laborers sourced by contractors as far as Manila and Pampanga. Assistant provincial engineer Lanie Daquioag confirmed this as she reported "there are some changes in the original plan and design." Known as the “Big 3” projects, the provincial engineering office said the on-going construction of the Provincial Capitol expansion building, reconstruction of the Dap-ayan Food Park, and the full rehabilitation of the President Ferdinand E. Marcos Memorial Stadium, all in the city of Laoag is only about 10 percent completed. Funded through a soft loan from the Development Bank of the Philippines during the last term of former governor and now senator Ma. Imelda Josefa “Imee" R. Marcos, t