By Dominic B. dela Cruz
Staff reporter
Paoay,
Ilocos Norte—The Dept. of Public Works and
Highways (DPWH)-Ilocos Norte Engineering District (INED) II advised that the
construction of the Sawang Bridge replacement in this town is still ongoing.
DPWH-INED II district
engineer Mathias Malenab said the PHP30 million first release of the Sawang
Bridge fund began in 2017 and continues up to present. He is hoping the
additional funding for its completion will be released soon. He estimated the
additional funding at less than PHP20 million.
The bridge construction was
delayed by the transfer of powerlines from the old, existing bridge to the new
bridge. DPWH has completed the said transfer.
He explained that the
45-meters bridge is located just beside the old Sawang Bridge, which is still
operational and open to small type of vehicles.
Earlier, DPWH-INED II
temporarily closed the said bridge from 9 am to 5 pm on April 16, 2019 to
launch the 40 meters type VI pre-stressed concrete girder (PSCG) at Sawang
Bridge.
North and south bound were
advised to take the Manila North Road (MNR), while those going to población
Paoay were advised to take the MNR via Batac-Paoay Road.
After the launch, Mr. Malenab
said the bridge is 70 percent complete.